Location
Bedourie, QLD
Project Type
PWD-accessible amenities block
10 Weeks
Build Time
Project Overview
Bedourie State School needed a fully accessible bathroom for a non-verbal student who uses a wheelchair. We designed and built it off site, coordinated trades from across far western Queensland, and delivered it through a four-month wet season delay that closed the roads entirely. The moment they reopened, we moved, finishing the install with just one weekend to spare before the rains returned.
The Challenge
The school needed a specialised bathroom for a non-verbal student who uses a wheelchair in one of the most remote communities in Queensland. The brief was clear: safe, dignified, durable, and reliably delivered, no matter the conditions. Wet season rains in far north Queensland severed the roads for four months. We waited, kept the school informed, and mobilised the moment the routes reopened. The team drove two days each way to complete the install and finished with just one weekend to spare before the roads closed again.